If it takes 10 men 4 hours to repair a barn, how long will it take 8 men to complete the task?

Respuesta :

RickyChen
RickyChen RickyChen
  • 13-07-2017
Let's assume it takes x hours.

People will be inversely related to hours, which makes more sense, sorry for my previous wrong answer.

Calculate the relationship: k = 10*4 = 40

So, 8x = 40, x = 5


Answer Link

Otras preguntas

guys help me please i really need Help with anything you could help me
A line contains the point (–3, 4). If the slope of the line is -2/3, write the equation of the line using slope-intercept form.
what is the outcome of beowulf's battle with grendel?
Which level of organization comes between a cell and an organ?
What is 69 over 24 as a terminating decimal
6 pens is $2.40 what is the cost of one
Which three factors were part of European Imperialism?
the ability to identify where you are, that is, locating your space and evaluating it in relation to someplace else, is known as ______.
the length of a rectangular suitcase is 7 inches longer than the width. the area of the suitcase is 144 squared inches.
why did the gods throw a rabbit at the moon