Every network has at least one critical path.
a. True
b. False

Respuesta :

Kalahira
Kalahira Kalahira
  • 24-01-2018
True and it is the longest path of a network diagram. The critical path can be found through the sequence of project activities that add up to the longest overall duration.
Answer Link

Otras preguntas

The oldest child in a family of four children is twice as old as the yougest. The two middle children are 13 and 16 years old. If the average age of the childre
You draw two cards from a standard deck of 52 cards and replace the first one before drawing the second. find the probability of drawing a 2 and a 6 in either o
1.En el año 2030, yo ______ 42 años. A.tengo B.tenia C.tendre
Physicians may withdraw or withhold aggressive life-sustaining treatment under which condition?
Bob Ewell is angry after the trial and stabs Atticus with a knife. True or False
What was the penalty countries incurred for not being part of the world trade system?
Discuss the relationship between exercise and heart disease
At each mile marker for the first five miles of a marathon, Ellie was 18 seconds, 9 seconds, 14 seconds, 6 seconds, and 3 seconds ahead of her goal pace. What w
How do you add and subtract fractions with the same denominator?
What is the solution for 3x-(2+4x)